Procurement & BIM check · public clients · amounts excl. VAT

Which rules does your building case trigger?

The construction sum decides how the works must be tendered, which BIM requirements apply, and whether the consultant can be bought without a tender. The use decides climate requirements and classes. Answer the questions and see the whole list — with the BIM requirements section by section.

Legal basis as at 22.09.2026Threshold values 2026–27No cookies, nothing is sentGuidance only — not legal advice

1The client

Who is building?The thresholds differ for central government and for everyone else

2The building case

What is going to happen?Conversion and renovation are not the same thing in the BIM regulation
DKK
m²
m²

3The digital side

The BIM requirements must be in the agreements before the parties have to meet them. That is why it matters how far the project has come.

Does the state pay at least half?A state loan or grant of at least 50 % — then the BIM requirements apply from DKK 5m
Is the renovation supported by the National Building Fund?Executive order 119 only covers supported renovations under the Social Housing Act ss. 91 and 92
Are you holding a design competition?Then the entries must be delivered as building models
Is the works contract tendered with quantities?Bills of quantities that the tenderers price

4Buying the consultant

SYNEGRO's fee follows the construction sum on a ladder from O1 to O5. Options and other purchases of consultancy of the same type in the case count towards the contract value.

DKK
DKK
Clear cross-border interest?Your own assessment — based on the amount, the nature of the task and the location
The checklist

This is what your building case triggers

Every point with the section it rests on. Points that do not hit your case are dimmed, so you can see why they do not apply.

The BIM requirements

The BIM requirements, section by section

The threshold values 2026–27
LimitAmount excl. VATWhat happens at the threshold
Negotiated quotes, at least two quotes300,000Public contracting authorities must obtain at least two quotes (the Tender Act s. 12)
Negotiated quotes prohibited3,000,000Above the amount the works contract must go to competitive tender (the Tender Act s. 12)
BIM, the state and construction the state finances by at least 50 %5,000,000Executive order no. 118/2013 s. 1(1), nos. 1–3 — at the amount or above
BIM, municipalities and regions20,000,000Executive order no. 118/2013 s. 1(1), nos. 4–6 — at the amount or above
BIM, social housing20,000,000Executive order no. 119/2013 s. 2 — new build and supported renovations
EU tender for the works contract40,313,840The Public Procurement Act, e.g. an open procedure with at least a 35-day deadline
Lots, building and civil works7,460,000Lots below the amount can be kept outside the EU tender, at most 20 % of the total value (the Public Procurement Act s. 8(2))
Lots, supplies and services596,800Same rule for advisory work and other services
Advisory work, advertising on udbud.dk100,000Where there is clear cross-border interest (the Public Procurement Act ss. 191–192)
Advisory work, market terms500,000Without clear cross-border interest (the Public Procurement Act s. 193)
Advisory work, EU tender — central government1,044,400Part II of the Public Procurement Act
Advisory work, EU tender — local authorities, regions, social housing1,611,360Part II of the Public Procurement Act

The threshold values change every other year — next time on 1 January 2028. The bill to repeal the Tender Act and introduce a national threshold of DKK 5m (L 113) lapsed at the general election in March 2026, so the Tender Act still applies.

What the BIM executive orders say
  • Executive order 118 s. 1(1). Applies to the construction, conversion and extension, renovation and maintenance of buildings and the civil works connected to them, when the estimated construction sum excl. VAT is DKK 5m or more for construction with the state as client (no. 1), construction the state finances with loans or grants of at least 50 % (no. 2), and construction for institutions whose operation the state pays at least 50 % of (no. 3). For regions and municipalities the same applies at DKK 20m (nos. 4–6).
  • Executive order 118 s. 1(2). Construction with a commitment of support under the Social Housing Act, the Private Care Homes Act or the Urban Renewal Act is not covered. Social housing follows executive order 119.
  • Executive order 118 s. 2. For renovation and maintenance the client may omit one or more requirements if the cost of meeting them is out of proportion to the gains (subsection 1) — but not s. 8 on digital tendering and bidding (subsection 2).
  • §§ 3–11. BIM coordination (s. 3) · digital building objects (s. 4) · digital communication and common data environment (s. 5) · building models in design competitions (s. 6) · object-based building modelling in design and construction (s. 7) · digital tendering and bidding (s. 8) · quantities (s. 9) · digital handover (s. 10) · digital defect lists (s. 11).
  • Executive order 119 ss. 1–2. Applies to social housing under the Social Housing Act s. 115, renovations under ss. 91 and 92(1) and (3), and design competitions for that construction, when a social housing organisation, a municipality or a region is the client and the construction sum is DKK 20m excl. VAT or more. Ss. 3–11 set the same requirements as executive order 118. There is no exemption for renovation.

Executive order no. 118 of 6 February 2013 applies to building projects started on 1 April 2013 or later. Executive order no. 119 of 7 February 2013 applies to construction with a commitment from the same date. Both are issued under the Public Construction Act and remain in force. Guidance no. 9188 of 6 February 2013 elaborates on the requirements.

How this is calculated

The works contract is assessed on the estimated construction sum excl. VAT. If the build is split into several contracts, it is the total value that counts.

The BIM threshold is DKK 20m or more for municipalities, regions and social housing — and DKK 5m for the state and for construction the state finances by at least 50 %. The phases in the matrix show which agreement the requirement must be in, and when it applies. If a moment has passed, the requirement must be agreed as a variation.

SYNEGRO's fee ladder is tied to the same thresholds: O1 below DKK 3m · O2 DKK 3–5m · O3 DKK 5–20m · O4 DKK 20–40.3m · O5 above DKK 40.3m. The fee for the full service from phase 0 to recommending contractors is DKK 314,000 · 455,000 · 827,000 · 1,199,000 · 1,654,000 excl. VAT.

The contract value is the fee plus options and extensions (the Public Procurement Act s. 30(1)) and other purchases of consultancy of the same type in the case, which are added together (s. 8). A purchase must not be split up to come under a threshold (s. 30(2)).

The climate requirement applies to new build and extensions (BR18 ss. 297–298). Only extensions below 250 m² to detached houses, terraced, linked and semi-detached houses, farmhouses and holiday homes are exempt — extensions to institutions are covered regardless of size.

Bring the list to a clarification meeting.

30 minutes, online or at your offices. No invoice. We go through how the purchase of the advisory services and the tendering of the works can be put together, which BIM requirements must be in the agreements — and what that means for the programme and the budget.

Send the check to us →

The button opens your own email program with the answers written in. Nothing is sent until you press send yourselves.
info@synegro.dk · +45 93 60 24 30 · weekdays 9–17